Seshen25 station report for Tog meeting in Onsala (July. 2005) 1. Observations Seshan station participates the FEB and JUN sessions/2005 for Astrophysics. One expriment was failed because of antenna and there were occasionaly problems for Mark 5 and disk driver ets. 2. Antenna The antenna drive and control system will be upgrade on July to Aug and will put into use in third EVN sessetion. 3. Field System New FS computor has been used since April this year. The FS system was updated to FS 9.7.7. 4. H-maser New MHM2010 maser works well since May 2004. 5. receiver There are no change. The L-band refrigeration double polarization receiver system will be got and intalled on next moonth. 6. Future plan 6.1 Developing Mini DBBC for Lunar project. 6.2 New S/X band receivers is being built for Sheshan and Urumqi telescopes.